Description

These are HGTD-IJS group meeting pages

 

https://cern.zoom.us/j/96207798641?pwd=STczWTN5YjFYTmlITFB3bEdPTE1MUT09 

 

 

PQC:
- NI DAQ replacement board was tested with the Chinese switching matrix. Document the cabling for the Monday Sensor meeting (JD)
- Relay board: hardware is connected and needs to be tested. Request code from USP (JD)
- Continue with setup commissioning

Database:
- Check with USP how QCTS are related to the corresponding main sensor/wafer -> Monday sensor meeting
- Upload all files so far (BH)

IT:
- Waiting for new package of USTC/IHEP samples to be delivered
- Prepare plan for overirradiation tests

Timing:
- Calibrate timing setup with Am241 (BH)
- Explore options to improve trigger purity
- Correlate TCT vs timing: GainTCT100V vs. ChargeAtXvolts (BH)

Long term stability:
- Begin starting thinking about setup preparations
- Check limits of HV ramp-up speed